Wuhan Huoshenshan Hospital took 10 days to build!

Heyagroup,constructioncompany,RealEstateIndustry,BuildingMaterialIndustryChinaHeyaGroupCompanyLtd.

Wuhan Huoshenshan Hospital took 10 days to build!


Location of Wuhan Huoshenshan Hospital



Day 1 --- (January 24th )

Hundreds of excavators arrived at the scene

Land leveling started



Day 2 --- (January 25th)

Wuhan Huoshenshan Hospital

Officially started



Day 3 --- (January 26th)

Complete the basic map of 6 nursing units

And the general plan of hydropower



Day 4 --- (January 27th)

Completed the site leveling

The first batch of box container board house hoisting and building



Day 5 --- (January 28th)

Steel structure of double-deck ward

Taking shape



Day 6 --- (January 29th)

More than 300 box-type frame houses

The installation is complete

The electromechanical pipeline operation starts simultaneously



Day 7 --- (January 30th)

HDPE film laying completed

Sewage treatment room equipment hoisting starts simultaneously



Day 8 --- (January 31st)

90% container assembly has been completed

3000 square meters of skeleton installation



Day 9 --- (February 1st)

Fully launched

Medical equipment installation



Day 10 --- (February 2nd)

Wuhan Huoshenshan Hospital officially delivered



Wuhan Huoshenshan Hospital